ARAMCO SAFETY SUPERVISOR WRITTEN EXAM QUESTION AND ANSWER PART 2



ARAMCO
SAFETY SUPERVISOR WRITTEN EXAM

QUESTION AND ANSWER
PART 2




QUESTION:

1. Why should the electrical panel board breaker list be regularly updated? Select the best answer

a)         For thorough record-keeping

b)         For isolation in case of emergency

c)         Too easy locking and tagging for regular maintenance

d)         To determine when breakers need to be replaced

 

ANSWER:

b. For isolation in case of emergency


QUESTION: 

2. Who is allowed to operate the crane?

a)         All contractor

b)         Trainer under the direct supervisor of a certified crane operator

c)         Saudi Aramco certified operators

 

ANSWER: 

c. Saudi Aramco certified operators


QUESTION: 

3. Which of the following lifts required critical lift plans?

a)         Operation inside a warehouse

b)         Operation inside the building construction

c)         Lifting a load that weighs 20 tons

d)         Lifting a large load that requires 3 cranes

ANSWER: 

d. Lifting a large load that requires 3 cranes


QUESTION: 

4. Who can complete the field inspection and tagging of a special scaffold taller than 6m or 20 ft? 

a)         Any Saudi Aramco employ

b)         Any contractor employee

c)         Scaffold inspector

 

ANSWER: 

c. Scaffold inspector


QUESTION: 

5. What must you do before you rely on a fall arrest system? 

a)         Attached a weight and let it fall

b)         Company name

c)         Inspect that fall arrest system

 

ANSWER: 

c. Inspect that fall arrest system


QUESTION: 

6. When working within one arm’s length of electrical equipment you should not wear which of the following. 

a)         Jewellery

b)         safety shoe

c)         Safety Glass

 

ANSWER: 

a. Jewellery



QUESTION: 

7. Who should inspect cranes prior to their use? Select the best answer.

a)         Contractor

b)         Shift supervisor

c)         Engineers

d)         Operations

 

ANSWER: 

d. Operations


QUESTION: 

8. When should Ground Fault circuit interruption be used? 

a)         At all times

b)         When using a portable electrical tool

c)         In the dump area

d)         When using temporary work

 

ANSWER: 

a. At all times


QUESTION: 

9. What is the minimum safe distance between an overhead power line up to 50,000 V (volts) and any part of a crane? Select the best Answer.

a)         1.8 m (6ft)

b)         2m (7ft)

c)         3m (10ft)

d)         6m (20ft)

 

ANSWER: 

C. 3m (10ft)


QUESTION: 

10. You are about to raise an elevating work platform. What should you do?

a)         Retract the outriggers so that the lift is easily moved

b)         Ensure you and tools carry are within weight limits

c)         Connect the lanyard of your harness to the anchor point

 

ANSWER: 

c. Connect the lanyard of your harness to the anchor point


QUESTION: 

11. What is the correct slope at which ladder6 should be used?

a)         3m horizontal for 1m vertical

b)         1m horizontal for 3m vertical

c)         4m horizontal for 1m vertical 

 

ANSWER: 

c. 4m horizontal for 1m vertical




QUESTION: 

12. Crane lift shall not be allowed at wind speed above…….unless otherwise specified by the manufacturer. Select the best answer.

a)         10 km/h (6mph)

b)         32 km/h (20mph)

c)         20 km/h (13mph)

d)         64 km/h ( 40mph)

 

ANSWER: 

b. 32 km/h (20mph)


QUESTION: 

13. Which of the following should have an inspection sticker before a crane lift? 

a)         The load

b)         LMI

c)         The rigging equipment

d)         The outrigger mates

 

ANSWER: 

c. The rigging equipment


QUESTION: 

14. Who can erect scaffolding shorten than 12.2m (40ft)? Select all items that apply.

a)         Any team of Saudi Aramco employees

b)         Approved specialist scaffolding erectors

c)         Any team of experienced contractors

 

ANSWER: 

b. Approved specialist scaffolding erectors

 

QUESTION: 

15. What should know the weight of before beginning a lift?

a)         The load

b)         The crane

c)         The rigging equipment

 

ANSWER: 

a. The load


QUESTION: 

16. When the crane is traveling how should the boom be positioned? Select the best answer.

a)         Raised with the hook free

b)         Raised with the hook secure

c)         Lowered with the hook free

d)         Lowered with the hook secure

 

ANSWER: 

d. Lowered with the hook secure


QUESTION: 

17. Above what weight are the critical lift plans required?

a)         50 tons

b)         40 tons

c)         30 tons

d)         20 tons

 

ANSWER: 

b. 40 tons


QUESTION: 

18. You have to work on a fixed elevated work surface. What should you do before working?

a)         Test by exceeding the maximum weight

b)         Test using a personal fall arrest system

c)         Look for and guard all floor openings

 

ANSWER: 

 c. Look for and guard all floor openings


QUESTION: 

19. How should personnel be transferred using a crane? Select the best answer.

a)         Slings

b)         Ropes

c)         Man baskets

d)         Mobile scaffold

 

ANSWER: 

c. Man baskets


QUESTION:

 20. You are performing high voltage work and are wearing all PPE. What after that may be required to provide insulation from energized or grounded.

a)         Conducting Mets

b)         Non-conducting Mats

c)         Conducting Blankets

d)         Non-conducting Blankets

 

ANSWER: 

d. Non-conducting Blankets
 